DEPARTMENT OF AGRICULTURE
AGENCY: USDA-Rural Development/Rural Utilities Service
NOTICE: Chamois-Maries Transmission Line Project, Missouri
Central Electric Power Cooperative has withdrawn its application for funding of this proposal. The Rural Utilities Service (RUS) will not be providing financial assistance for this proposal. A NEPA decision document will not be developed by RUS or posted to this website.
Central Electric Power Cooperative proposes to rebuild approximately 49 miles of 161kV transmission line between the Chamois, Rich Fountain, Vienna, and Maries Substations. The proposed Chamois – Maries project is located in Osage and Maries Counties, Missouri.
Notice of Availability (NOA) of the Environmental Assessment – October 18, 2022
Environmental Assessment (EA) – September 2022