Project Description: The Project area has been previously disturbed for agriculture activities. The current site is a flat, open field that would require minimal grading. The disturbance of land would be limited to the approximately 17-acre Project area during construction. The site is adjacent to existing Eau Claire Energy Cooperative (“the Cooperative”) distribution lines that would allow for ease of interconnection. The Applicant and Eau Claire Energy Cooperative have an interconnection agreement that allows for interconnection of the Bridge Creek Solar Project to the existing 12.47 kilovolt (kV) distribution line along County Rd V.
Project Submittal Date: March 2025
Project Approval Date: 3/12/25
DOE CatEx Applied: B5.16